Kranji Expressway is Singapore’s eighth expressway.1 Built between 1994 and 1995, it is 8.4km long. It links the Bukit Timah Expressway (BKE) and the Pan-Island Expressway (PIE), at the Tengah flyover, near Hong Kah.2

History

In 1990, the Public Works Department received a S$1.1 billion budget from the government to develop and construct a network of expressways and roads throughout the island over a period of five years.3 This was in tune with the government’s plan to develop the northern and western parts of Singapore into residential and industrial places of choice.4 The road development work included widening, expanding and re-aligning portions of existing expressways, such as the PIE, BKE and CTE (Central Expressway). It also included building underground roads, tunnels, viaducts, semi-expressways and flyovers. The construction of 13 new interchanges and the construction of a road linking BKE and PIE were also included in the plan. This new road was probably named Kranji Expressway as it passed through the Kranji estate in Woodlands, connecting it to Jurong, Choa Chu Kang and Bukit Panjang.5


Construction of the expressway began in April 1990 and it was completed in six stages.6 One of the more difficult jobs in laying the expressway was the clearing of a 1,000 cu m large granite outcrop along the way, for which 300 kg of explosives was used.7 The expressway project comprised five different contracts covering different jobs in the road construction.8

Both the PIE and the AYE were concurrently developed. The PIE was developed at a cost of S$180 million and it was extended until Tuas. Construction of this work began in 1991 and it was completed in 1994.9 Similarly in 1993, the existing Jalan Ahmad Ibrahim was upgraded and extended from Jurong Town Hall Road to Tuas, thus incorporating it into the existing AYE.10 This development was completed in 1997.11 The existing AYE until then only connected the junction of CTE and East Coast Parkway to Jurong Town Hall Road.12

The entire network of linking roads came about by the construction of KJE connecting the BKE in Woodlands to the PIE at Hong Kah,13 the extension of PIE from Hong Kah to Tuas and the extension of AYE from Jurong Town Hall Road to Tuas to join the PIE.14 This extensive network improves accessibility, and enhances residential and industrial development for the western and northern regions of the island.15 Its most marked effect was on the Choa Chu Kang estate which it helped transform from a backwater town into a thriving housing estate.16

Description
The KJE has six flyovers. Beginning at the Tengah Flyover, it is linked to Brickland Road at the Lam San Flyover (Exit 5), to Choa Chu Kang Way at the Choa Chu Kang West Flyover (Exit 4), to Choa Chu Kang Drive at the Choa Chu Kang East Flyover (Exit 3), to Woodlands Road at the Yew Tee Flyover (Exit 2) and to Bukit Timah Road at the Gali Batu Flyover (Exit 1).17

One unique feature of the KJE was the use of a special tar-like asphalt substance as a surface material to minimise the risk of skidding. KJE was one of the first few roads to feature this new surfacing in 1994 which cost S$6.1 million.18 This anti-skid feature was later incorporated into other roads as well.19 The Kranji Expressway was inaugurated on the 4 March 1995 by the Acting Development Minister Lim Hng Kiang.20

Kranji Expressway serves residents of Bukit Panjang, Choa Chu Kang, Bukit Batok and Jurong.21 As it connects Jurong to Woodlands, the expressway is a faster alternative to Malaysians who travel here from Johor to work in factories in Jurong and Tuas.22 Slip roads have been built to provide access between roads at ground level and the expressways.23


Significant construction along the expressway include private and public housing units, most of which were constructed after the laying of the expressway in 1994.24 The Yew Tee MRT which opened with the rest of the Woodlands MRT Line on 10 February 1996 also played a pivotal role in the development of Choa Chu Kang estate.25 The URA released its Development Guide Plan in 1996, soon after the opening of the Yew Tee MRT, with the vision of transforming the Choa Chu Kang estate into a residential district.26



Author

Naidu Ratnala Thulaja




References
1. Dhaliwal, R. (1995, March 5). $1.9 b for roads over next 5 years. The Straits Times, p. 3. Retrieved from NewspaperSG.
2. Blasting resumes for Kranji Expressway. (1993, October 15). The Straits Times, p. 25. Retrieved from NewspaperSG.
3. Dhaliwal, R. (1995, March 5). $1.9 b for roads over next 5 years. The Straits Times, p. 3; Dhaliwal, R. (1990, February 5). Expressway network ready within 5 years. The Straits Times, p. 19. Retrieved from NewspaperSG.
4. Work on Kranji Expressway's second phase under way. (1991, October 31). The Straits Times, p. 18. Retrieved from NewspaperSG.
5. Kranji Expressway (KJE). (2013, January 18). Retrieved on 2016, May 11 from LTA website: https://www.lta.gov.sg/content/ltaweb/en/roads-and-motoring/projects/kranji-expressway-kje.html
6. Expressway will benefit Bukit Batok, Jurong, Bukit Panjang, Choa Chu Kang residents. (1994, June 12). The Straits Times, p. 26. Retrieved from NewspaperSG.
7. Blasting resumes for Kranji Expressway. (1993, October 15). The Straits Times, p. 25. Retrieved from NewspaperSG.
8. Kranji Expressway: Work begins on Choa Chu Kang interchange. (1992, October 3). The Straits Times, p. 25; Work starts on Kranji/ Woodlands interchange (1992, July 25). The Straits Times, p. 22. Retrieved from NewspaperSG.
9. PIE will reach Tuas by ‘94. (1992, January 8). The Straits Times, p. 3. Retrieved from NewspaperSG.
10. Ayer Rajah Expressway to be extended all the way to Tuas. (1993, December 5). The Straits Times, p. 30. Retrieved from NewspaperSG.
11. Chan, M. F. (1997, November 18). AYE extension to Tuas opens, The Straits Times, p. 36. Retrieved from NewspaperSG.
12. Ayer Rajah Expressway to be extended all the way to Tuas. (1993, December 5). The Straits Times, p. 30. Retrieved from NewspaperSG.
13. Kranji Expressway: Work begins on Choa Chu Kang interchange. (1992, October 3). The Straits Times, p. 25. Retrieved from NewspaperSG.
14. Ayer Rajah Expressway to be extended all the way to Tuas. (1993, December 5). The Straits Times, p. 30. Retrieved from NewspaperSG. 
15. Northern region: home to private industrial developments. (1995, July 13). The Business Times, p. 2; Tan, C., & Yeo, S. (1996, May 19). Choa Chu Kang: on the fast track to growth. The Straits Times, p. 5. Retrieved from NewspaperSG.
16. Tan, C., & Yeo, S. (1996, May 19). Choa Chu Kang: on the fast track to growth. The Straits Times, p. 5. Retrieved from NewspaperSG.
17. Public Works Department (1994/5) Annual report / Public Works Dept.. Singapore: Public Works Department, p. 10. (Call no.: RSING 354.59570086 SIN-[AR]); Kranji Expressway. Retrieved on 2016, May 11 from Singapore Street Directory website: http://www.streetdirectory.com/sg/kranji-expressway-kje-exit-1-from-pie-towards-bke-near-gali-batu-flyover/19574_1.html
18. Leong, C. T. (1994, June 12). New Kranji Expressway to have safer rainy-weather road surface. The Straits Times, p. 26. Retrieved from NewspaperSG.
19. Leong, C. T. (1994, June 12). New Kranji Expressway to have safer rainy-weather road surface. The Straits Times, p. 26; Dhaliwal, R. (1993, December 5). PIE extension opens with better skid-resistance. The Straits Times, p. 30; Dhaliwal, R. (1995, March 5). $1.9 b for roads over next 5 years, The Straits Times, p. 3. Retrieved from NewspaperSG.
20. Dhaliwal, R. (1995, March 5). $1.9 b for roads over next 5 years, The Straits Times, p. 3; Retrieved from NewspaperSG.
21. Expressway will benefit Bukit Batok, Jurong, Bukit Panjang, Choa Chu Kang residents. (1994, June 12). The Straits Times, p. 26. Retrieved from NewspaperSG.
22. Expressway will benefit Bukit Batok, Jurong, Bukit Panjang, Choa Chu Kang residents. (1994, June 12). The Straits Times, p. 26. Retrieved from NewspaperSG.
23. Kranji Expressway: Work begins on Choa Chu Kang interchange. (1992, October 3). The Straits Times, p. 25. Retrieved from NewspaperSG.
24. Tan, C. (1996, May 17). URA to turn Choa Chu Kang into choice residential district. The Straits Times, p. 64. Retrieved from NewspaperSG.
25. Lim S.T. (1996, January 27). Time and money savings for some MRT commuters, The Straits Times, p. 3. Retrieved from NewspaperSG.
26. Tan, C., & Yeo, S. (1996, May 19). Choa Chu Kang: on the fast track to growth. The Straits Times, p. 5. Retrieved from NewspaperSG.



The information in this article is valid as at 2016 and correct as far as we are able to ascertain from our sources. It is not intended to be an exhaustive or complete history of the subject. Please contact the Library for further reading materials on the topic. 


Rights Statement

The information on this page and any images that appear here may be used for private research and study purposes only. They may not be copied, altered or amended in any way without first gaining the permission of the copyright holder.

More to Explore

Tanjong Rhu Road

ARTICLE

Tanjong Rhu Road begins from the junction of Fort Road and Meyer Road, and ends near the Marina Reservoir. It runs parallel to the East Coast Parkway while part of the Kallang-Paya Lebar Expressway runs under Tanjong Rhu Road. This road used to be a marine yard and the centre...

Nicoll Highway

ARTICLE

Nicoll Highway stretches westward from Mountbatten Road across the mouth of Kallang River over Merdeka Bridge down to the city centre, where it joins Connaught Drive and Stamford Road. It was built in the 1950s to alleviate frequent traffic jams on the often congested Geylang and Kallang roads during peak...

Woodlands MRT station

ARTICLE

The Woodlands Mass Rapid Transit (MRT) station was constructed as part of the Woodlands MRT line, built in the early 1990s, which connects Choa Chu Kang to Yishun. Located directly under the Woodlands station is Singapore’s first underground bus interchange. ...

Fort Fullerton

ARTICLE

Fort Fullerton was one of the earliest forts built in Singapore, predating even Fort Canning. It was located at the mouth of the Singapore River and constructed with the aim of protecting the ships in the harbour. The fort was subsequently demolished and replaced by the Post Office in 1882,...

Kallang

ARTICLE

Kallang is bounded by the northeastern boundary of the Central Area, the Central Expressway, the Pan Island Expressway, the proposed Kallang Expressway, Mountbatten Road and the East Coast Parkway. It covers nine subzones and a total area of 920.7 ha. Some of Singapore’s earliest settlers lived in Kallang. They were...

Labrador Park/Fort Pasir Panjang

ARTICLE

Labrador Park/Fort Pasir Panjang, former defence battery, nature park and designated reserve area, is located in Singapore’s Central Region. The name Labrador is derived from “Labrador Villa”, the name of the residence of prominent ship chandler, George John Mansfield, built in 1881. Known as Fort Pasir Panjang, it was one...

Swan & Maclaren

ARTICLE

The famous colonial architectural firm Swan & Maclaren had its beginnings in 1887 as Swan & Lermit. It is considered to be one of the pioneer architectural firms in Singapore. Archibald Swan and Alfred Lermit, started Swan & Lermit, but the latter left the partnership in 1890. Swan, an engineer...

Outram

ARTICLE

Outram is a planning area in Singapore’s Central Region. It is bounded by Havelock Road and Pickering Street to the north, Telok Ayer Street, Peck Seah Street and Stanley Street to the east, Gopeng and Kee Seng streets to the south, and Cantonment Road and Outram Road to the west....

Ceylon Road

ARTICLE

Located in the eastern part of Singapore in the Joo Chiat/Katong district, Ceylon Road connects East Coast Road and Crane Road. The road was named after the island Ceylon (now known as Sri Lanka), as a large Ceylonese Tamil community had settled down around the area in the 19th century....

Tampines Expressway (TPE)

ARTICLE

Tampines Expressway (TPE) runs from the junction of Seletar Expressway (SLE) and Central Expressway (CTE) at Yio Chu Kang in the north to the Pan-Island Expressway (PIE) at Changi in the east. Built at a cost of S$120 million, construction of the 14.4 km expressway was completed in 1996. It...